Hearnigs impacting local customers are in April and May.
The Public Utilities Commission of Ohio has established a procedural schedule to consider Dayton Power and Light’s market rate offer application. The proceedings will allow PUCO staff, the public and other stakeholders to present testimony regarding the utility’s proposal.
The procedural schedule includes hearing dates at the Columbus PUCO office on:
April 12, 2012: The PUCO will host a technical conference to help stakeholders better understand DP&L’s application. The conference will begin at 9 a.m. at the PUCO offices, 180 E. Broad St., Hearing Room 11-B, Columbus.
April 20, 2012: Motions to intervene due. Comments due from PUCO staff.
April 23, 2012: A prehearing conference will begin at 10 a.m. at the PUCO offices, Hearing Room 11-A.
April 26, 2012: Testimony due from intervenors.
May 8, 2012: An evidentiary hearing will begin at 10 a.m. at the PUCO offices, Hearing Room 11-A.
DP&L filed an MRO application with the PUCO on March 30, 2012. In the application, DP&L proposes to use a competitive bidding process to set customers’ electric generation rates from January 1, 2013 through May 31, 2018.